RESTART OF PROJECTS IN AKAMAS IN FEBRUARY - WHEN WILL ALL PHASES AND INFRASTRUCTURES BE COMPLETED?




RESTART OF PROJECTS IN AKAMAS IN FEBRUARY - WHEN WILL ALL PHASES AND INFRASTRUCTURES BE COMPLETED? - Filenews 16/11


With the aim of completing Phase A of the road network of the Sustainable Development Plan of the Akamas National Forest Park (SARP) on 28/2/2028, the tender was announced on 6/11/2026, with the estimated value amounting to €5,630,000 (€6,694,000 including VAT). The projects are estimated to start in February 2027 with 13 months of implementation.

The project is part of the strategic planning for safe access, sustainable mobility and strict environmental protection of the sensitive Akamas area. Today the Park receives over 400,000 visitors.
The main purpose of the Plan is the protection of biodiversity and the natural environment through the organized management of traffic, in combination with the supervision of the Park, operating rules, conservation measures and informing the public. In this context, provision was made, among other things, for a defined road network, limitation of uncontrolled access, organized visitor service infrastructure, alternative modes of transportation and an environmental monitoring program.

The works were suspended on 11/12/2023 and today the unfinished road network presents maintenance, drainage and safety problems, while the full implementation of the organized management measures of the National Forest Park is delayed.

It is noted that the project is a prerequisite for the Park to function as a protection tool in practice with controlled access, park guard, safe movement of visitors and the possibility of timely intervention in case of fire.

The project is co-funded, which underlines its importance for green growth and infrastructure. Specifically, 60% of the expenditure is covered by the Cohesion Policy Program "THALIA 2021-2027", while the remaining 40% is financed by national resources.

The process will be completed with the opening of the tenders on 8/12/2026 on the same day that the tenders will be submitted in the presence of the competent evaluation committees.

Phase A focuses on the improvement of three key roads with a total length of approximately 9.9 km:

• Road 1A (Aspros Potamos – Toxeftra – Lara) 6.2 km long. approximately, it is the main trunk of the passage to the coast of Lara.

• Road 2 (Laras Roundabout) 2.7 km long. designed to facilitate circulation around the turtle protection area.

• Road 4B (Toxeftra – Avakas) 1.0 km long. approximately, which leads to the entrance of the impressive gorge of Avakas. In addition to the road projects, the construction of an organized parking lot in the area of Lara is included. It is noted that there are seasonal work bans for the nesting of turtles and the reproduction of birds.

This intervention is considered crucial, as it aims to limit uncontrolled parking on sensitive ecosystems and to organize visitors before entering the absolute protection zones of the National Forest Park.

The project has been approved for inclusion in the THALIA 2021-2027 program, and for this reason it will be subject, in addition to the financial control exercised by the Contracting Authority, to an additional control body. The General Accounting Office, which verifies the financial expenses and also certifies the expenses to the EU as well as by the Intermediate Body (Audit Directorate of the Ministry of Transport, Communications and Works), for the implementation of the physical object of the Contract.

Regarding the cost of Phase A, payments were made based on invoices and certifications, while the pending issue with the Contractor was resolved by an amicable settlement, with the participation of the Legal Service and the approval of the Ministry of Finance.

It is emphasized that the most serious violations of legally binding terms of the environmental approval for Phase A of the improvement of the road network of the Akamas National Forest Park (SAR) were identified and denounced, as early as October 2023, by environmental organizations (Terra Cypria, BirdLife Cyprus, Cyprus Wildlife Society, Initiative for the Rescue of Natural Coasts and Federation of Environmental Organizations of Cyprus), representatives of whom participated in the evaluation procedures of the Sustainable Development Plan of the Akamas SAR and in the work of both the Ad-hoc Committee for the Special Ecological Assessment (EOA) and the Environmental Impact Assessment Committee. This raises serious questions regarding the implementation of the terms of environmental approval by the Department of Forests and the monitoring of the terms of environmental approval by the Department of Environment.

By the end of 2028, all phases and infrastructure will be completed

After the suspension of the works, it was decided to modify the design, with the aim of reducing the environmental footprint and addressing the additional technical and environmental requirements. With the completion of the basic environmental assessments in 2021, the implementation of Phase A of the road network began on 27/10/2022 with an end on 27/12/2023. Due to the issues that arose during construction, they led to suspension on 11/12/2023 with 17.67% of the project and 94% of the time previously executed. Following decisions of the Council of Ministers dated 20/12/2023 and 11/3/2024, planning with reduced interventions was promoted to further reduce the environmental footprint of the projects. This was followed by a Supplementary Special Ecological Assessment Report in 2024 and a Compliance Report of the Environmental Authority in 2025, while today the implementation of a revised design with increased environmental safeguards is being promoted.

The works of all phases and infrastructures are completed by 15/11/2028, with a defect liability period of 12 months. The habitat restoration follows the completion of the works of Phase A'.

1. Phase A of the road network (with Lara parking lot). The amended construction plans were approved on 31/7/2026. The Intermediate Audit Body requested on 30/9/2026 a revision of technical terms and the conversion of environmental terms into contractual ones.

2. Information/recreation infrastructure (hubs). The tender was announced on 24/8/2026 and an offer has been received, which is being evaluated by the Department of Forests. It is noted that the previous tender of 2022 (revised estimate of €6.59 million) was cancelled due to the submission of a single bid with an expenditure exceeding the revised estimate of €8.9 million.

3. Aphrodite Baths – Amoroza Fountain Road. Cost €160,000. The earthworks (about 3 weeks) started on 9/11/2026, and the installation of safety barriers is expected by mid-December. The forest road Loutra Aphrodite – Fontana Amorosa presents significant safety problems and is used by visitors and competent services. The proposed improvement is primarily aimed at ensuring safe access for fire trucks and other emergency vehicles.

4. Hydrological/hydraulic study (Avakas – Toxeftra). The final study was delivered on 16/10/2026 and is being evaluated.

5. Phase B. From 1/11/2026 (Lara – Ai Minas study) to 15/11/2028.

White River – Mundiko and Koutsagas – Tzifin by 2027.

6. Phase C' Works 1/1/2028 – 1/8/2028

Cutting off irregular accesses 1/8- 3-/9/2028.

7. Habitat restoration. After the end of the works of Phase A'